It is less than two months to puck drop at Belleville’s Yardmen Arena, home of the Belleville Senators.
Around 75 construction and trades workers are inside the building erecting concrete block walls, drywall, tech equipment and more
It is all ahead of the November 1st home opener.
Project Manager Peter Lyng says the last two weeks have been fast and furious.
Lyng says the players area is almost complete.
The new north end seating will arrive next month, the boards and meshing will go up and the refrigeration unit will be commissioned.